Electricians - have questions?

You should always call 000 straight away if there’s an emergency – like if you smell a gas leak, or if there’s any risk to someone’s life or property (you can find more details about that here).

If your power or gas goes out, or there’s a fault, contacting your distributor is usually the best place to start. If there’s an outage, they’ll usually be able to tell you when your power or gas should be back up and running.

Find distributor

If you're not sure whether there's an electricity supply at the site, you can check with the distributor.

Distributors are each responsible for set geographic areas – so yours will depend on where you live. You may even find that there’s more than one distributor in your postcode.

Find distributor

Read about the process and timeframes for electricity meters here.

There are a couple of things that’ll affect the cost of installation, including the state you live in and the distributor in your area. You can find a full list of the fees related to meter installations, alterations and abolishment here.

With Origin’s Connect Assist portal, you can submit new connection requests for electricity, natural gas and LPG – and you can also track the progress of each connection, ask questions, complete account closures and request final reads. It’s a complete connection management tool and it’s easy to Register.

You’ll need to get your electrical paperwork submitted as soon as you can, and make sure there’s clear access to the electricity meter box. We can let the meter provider and your distributor know the connection’s urgent – but keep in mind, they’re booked weeks in advance, so there’s no real way to fast track the process.

Timeframes are set by the meter provider and/or the distributor, and can depend on things like weather and the complexity of your job. But to avoid hold ups, it’s a good idea to submit your forms early in the construction process, and make sure they’re filled out correctly. You should also check that the site is clear and ready, and that the account’s in the client’s name when you submit the initial 'Request for a new energy account' form. You'll find all the forms you need here - just click on your state tab first.

Sometimes, a network field crew need to go onsite along with the electrical contractor to perform works that couldn’t be done otherwise – they may need to disconnect an overhead supply, or connect a new underground connection. The appointment date and time will be pre-booked.

Standard works like solar metering or new connections don’t need a truck appointment – unless there’s something non-standard that needs to be done as well.

Generally no – these jobs usually take longer. This is because appointments are needed and there’s more than one property at the site.

For newer sites, it’s not uncommon for the address to be pending finalisation. But you can check for the most accurate address and you should use that to complete your paperwork.

VIC: www.land.vic.gov.au
NSW: maps.six.nsw.gov.au