The team at Eraring regularly undertake significant projects to improve the operational performance of the power station and reduce its impact on the local environment and community.
Current projects include:
Major maintenance outages
Each year Origin typically performs a scheduled major maintenance outage on one of Eraring’s four generating units to ensure the safe, flexible and reliable operations of the power station.
During these scheduled maintenance outages, Origin will conduct a series of inspections and repairs to a generating unit’s boilers, turbine and cooling water systems to ensure the unit continues to meet its safety and regulatory requirements.
These maintenance outages take place during the spring shoulder periods so the unit can be available for the summer peak and sees an additional 500 workers on site.
Battery
In 2023 Origin commenced construction of a large-scale battery at Eraring. Large-scale battery energy storage systems play an important role in the energy transition, by supporting renewable energy sources and providing firming capacity and stability to the National Electricity Grid.
The Eraring BESS currently includes two main stages, with an additional stage of development in planning.
Eraring Battery 1 reached the final phase of commissioning in December 2025 bringing online 460MW of capacity with a dispatch duration of approximately four hours.
Eraring Battery 2 is currently under construction and is scheduled to commence operations in the first quarter of 2027. Once operational, it will provide 240MW of capacity and a dispatch duration of approximately 5.8 hours, helping to support grid stability and enabling greater integration of renewable energy into the system.
Origin is now seeking planning approval to expand the Eraring Battery through the addition of a 500MW, 8-hour battery on 11 hectares of land adjacent to Eraring Battery 1 and 2. The proposal is in the early stages of the planning and environmental assessment process, with technical studies, environmental investigations, and stakeholder consultation currently underway.
For more information and to keep up-to-date, visit the Eraring battery project site.
Southern Embankment Stabilisation Project
This project aims to strengthen and stabilise the southern embankment of the Eraring Ash Dam to ensure it is compliant with Dam Safety NSW requirements.
The project comprises two key components; enabling works and stability works.
The enabling works include the construction of a new internal construction road to provide access for all vehicles required during project delivery. A new on-site borrow pit will also be established during this part of the project to provide fill for the stability works.
Stability works will involve a stone column ground improvement technique, which will be complemented by an earthfill buttress.
Work is anticipated to commence in Q4 2022 and be completed in Q4 2024.
Flexible operations
In 2019, the team at Eraring conducted a flexible operations trial program to better understand how to align Eraring’s generation units with future changes in demand. These trials have provided insights into how best to improve Eraring’s flexibility to support the continued growth in renewable generation, while ensuring safe and efficient operations.
Real Time Optimisation
During 2019, Origin deployed an Australian-first digital tool to optimise Eraring’s performance. The Real-Time Optimisation project involved the installation of an Artificial Intelligence software application that removed the need to undertake manual calculations to identify efficiency improvements.
This project has already helped Eraring use less coal for the same MW, which means an overall reduction in emissions. This project aims to reduce the Station’s CO2 emissions by 1 million tonnes by 2025.
Ash dam expansion
On 23 December 2019, the NSW Independent Planning Commission approved Origin’s application to modify an earlier major project approval (MP 07_0084) for the Eraring Ash Dam.
The approved modification application enables Origin to:
- extend the ash dam placement area
- relocate ancillary infrastructure
- modify storm water management system on the western side of the Ash Dam
This expansion will have no material impact on the stability of the ash dam wall as the works will be occurring 600 metres from the main embankment.
More information is available at the NSW Government’s Department of Planning, Industry and Environment project portal website and on our Documents and Resources page.
Community Consultative Committee (CCC)
There were several approval conditions set down by the Independent Planning Commission, including the establishment of a Community Consultative Committee that will comprise of:
- an independent chairperson
- up to 7 community and stakeholder representatives
- a Council representative
- up to 3 representatives from Origin