Helping us meet customer demand for cleaner energy and contribute towards our ambition to be net zero emissions by 2050.
Our priority renewable energy project is the Yanco Delta wind farm in NSW, and we’re building large scale battery energy storage systems at our Eraring and Mortlake power stations, while also owning other large-scale wind developments.
Onshore wind development projects
Yanco Delta Wind Farm
Location: 10km north-west of Jerilderie, NSW
The 1.5GW Yanco Delta Wind Farm project is located on a 33,000-hectare site next to key transmission infrastructure in the NSW South-West Renewable Energy Zone. The project has received both New South Wales Government development approval (December 2023) and EPBC approval (February 2024) making it one of the largest and most advanced wind projects in New South Wales.
Current Status: To facilitate project design adjustments, Origin has made additional EPBC Act referrals (in April/May 2025) and submitted a Modification Report to the NSW Department of Planning, Housing and Infrastructure (in February 2026).
To learn more about the Yanco Delta Wind Farm development, visit the project website: www.yancodelta.com.au
Skye Ridge Wind Farm
Location: 10km west of Walcha, NSW
In February 2024, Origin confirmed the acquisition of the project from renewable developer Walcha Energy. Located in the southern part of the NSW Government designated New England Renewable Energy Zone, the Skye Ridge Wind Farm has a potential maximum output of 870MW.
Current Status: Origin’s current focus is on engaging with landowners and the local community and completing the technical studies required for a scoping report which will inform a future Environmental Impact Statement (EIS). Origin completed installation of wind monitoring masts in October 2024.
To keep up-to-date with this project and others we’re pursuing in the New England Renewable Energy Zone, visit the Origin New England site.
Northern Tablelands Wind Farm (Warrane)
Location: 18km north-west of Armidale, NSW
Origin completed the purchase of the 7,586 hectare ‘Warrane’ property (now also known as the Northern Tablelands Wind Farm) in July 2023. Situated within the New England Renewable Energy Zone, the Northern Tablelands Wind Farm has a high-quality wind resource and range of grid connection options which make it an attractive prospective wind development. In October 2023 Origin entered a lease arrangement with pastoral operator Palgrove, ensuring agricultural operations will coexist during wind farm development and proposed project.
Current Status: Origin completed the installation of two wind monitoring masts in May 2024 and has also commenced comprehensive environmental assessments across the property. At the same time, Palgrove will deliver an extensive pasture improvement program to support their broader cattle operations.
To keep up-to-date with this project and others we’re pursuing in the New England Renewable Energy Zone, visit the Origin New England site.
Eraring Power Station battery
Location: Eraring, approximately 120km north of Sydney and 40km south of Newcastle, NSW
Construction is underway on a large-scale battery energy storage system at our Eraring Power Station. The approved battery has a peak output of 700 MW for an average of 4.5 hours (or lesser loads for longer periods) making it one of the largest battery developments in the southern hemisphere. Locating the battery at Eraring takes advantage of the existing transmission and grid connection infrastructure, minimising the need for construction of long transmission lines. Once complete, the project will support more variable renewable energy coming into the system and help keep the grid stable.
Current Status:
Eraring Battery 1 commenced commercial operations in December 2025 bringing online 460 MW of capacity with a dispatch duration of approximately four hours. Eraring Battery 2, anticipated to come online early in 2027, will add a 240 MW / 1390 MWh grid-forming battery.
Origin is seeking planning approval to expand the Eraring BESS to include an additional 500MW, 8-hour battery on 11ha of land adjacent to Eraring Battery 1 and 2. The proposal is in the early stages of the development approval process focused on technical and environmental investigations and stakeholder consultation.
For more information and to keep up-to-date, visit the Eraring battery project site.


Mortlake Power Station battery
Location: 12km west of Mortlake, Victoria
Origin is constructing a large-scale battery with a peak generation output of 300 MW and a storage capacity of 650 MWh adjacent to Origin’s gas-fired Mortlake Power Station.
This project is located within the Victorian South-West REZ V4 region having been identified a key piece of infrastructure by the Victorian Government in its Renewable Energy Zone roadmap. The battery will be connected into the 500kV network that runs through the power station.
This Project received funding from the Australian Renewable Energy Agency (ARENA) as part of ARENA’s Advancing Renewables Program.
Current Status: Following a period of detailed design activity, the first phase of construction focused on site preparation and civil works, commenced in September 2024. The project is now in commissioning phase and targeting commercial operations in mid-2026.
For more information and to keep up-to-date, visit the Mortlake battery project site.
Project Documents:
Darling Downs Power Station battery
Location: Darling Downs Power Station, Kogan, 50km west of Dalby, Queensland
Origin is seeking approval to construct a 500MW battery with a storage capacity of up to 2,000 megawatt hours. The battery will be installed beside Origin’s Darling Downs Power Station which is Australia’s largest combined cycle gas fired power station with an overall generation capacity 630MW. When developed, the battery at Darling Downs will be charged via the existing grid connection during the day when renewable energy is plentiful and dispatched at times of peak demand.
Current Status: In August 2022, Western Downs Regional Council approved Origin’s Material Change of Use application to allow for the development and installation of a battery at the Darling Downs Power Station. Origin will undertake a tender process to identify a suitably qualified contractor to supply and install the battery.
Project Documents:

Templers Creek battery
Location: Templers, 4km west of Freeling, South Australia
The Templers Creek battery is a proposed 200 MW battery with a storage capacity of up to 800 megawatt hours. The Templers Creek battery will be located adjacent to the Templers West Substation on Templers Road, west of Freeling. When developed, the battery will be able to charge via the electricity network during the day when renewable energy is at its highest and discharge during peak demand.
Current Status: The Templers Creek BESS is an advanced stage development having completed site investigations and comprehensive technical, environment and social assessments.
Gas fired peaking power station developments
Kerrawary Power Station
Location: Big Hill, near Marulan, NSW Southern Tablelands
If developed, Kerrawary would provide up to 1,200 MW of fast-start, dispatchable generation, with a planned capacity factor of up to 15%. The project would be designed to provide flexible, dispatchable capacity to assist with maintaining a reliable electricity supply for NSW as coal-fired power stations retire and more renewable generation enters the system.
Origin is in the early stages of planning for the proposed development of the Kerrawary Power Station (KPS), an open-cycle gas turbine peaking power station on Origin-owned land at Big Hill, near Marulan in the NSW Southern Tablelands. The project also includes an associated gas pipeline of up to 35km, connecting the power station to the Moomba Sydney Pipeline.
Current Status: Origin is at an early, pre-EIS stage of planning, having recently concluded community consultation on the project’s Scoping Report. This report includes feedback from the local community, landholders and councils and will inform matters examined in an eventual Environmental Impact Statement. If the development proceeds, and subject to approvals, construction could commence in 2029, with operations from 2033. For more information and to keep up-to-date, visit the Kerrawary Power Station project page