We are planning for the retirement of the Eraring Power Station and the decommissioning of the Eraring site.

Preparing for closure
With the retirement of the Power Station scheduled to take place before the end of the decade, we have begun planning for the site’s eventual decommissioning. To support this, we are beginning work to secure the necessary approvals for demolition and rehabilitation of the site and Power Station infrastructure.
Following closure of coal-fired power generation at Eraring Power Station, we will be making significant changes to the site. These will include:
- retiring operational features,
- demolishing some of the site infrastructure, and
- undertaking rehabilitation work across the site.
Some of these changes will require statutory approvals through various regulatory authorities. We are beginning work to secure the approvals necessary for the decommissioning of the Eraring site and are undertaking studies to refine our approach to this process.
Obtaining these approvals is a critical step in rehabilitating the Eraring site to a safe and stable condition following the retirement of coal fired-power generation.
The approvals process
Our plans for the decommissioning of the site will require approval through the NSW State Significant Development (SSD) assessment process. This is a lengthy regulatory process that involves consultation with the community and stakeholders and investigations to assess the potential social and environmental impacts of the work. Origin will also seek approval from the federal government, in accordance with the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).
We are currently in the early phases of the SSD process, undertaking long lead environmental studies, technical investigations, and early engagement with key stakeholders to inform the preparation of an Environmental Impact Statement (EIS).
The following is the anticipated timings for each stage of the SSD process.

Anticipated timings for each stage of the SSD process:
2025 – mid 2026
Origin begins planning and long-lead investigations.
Late 2026
Origin outlines the project and key matters to be assessed during the development of the Environmental Impact Statement (EIS) as part of a request for Secretaries Environmental Assessment Requirements (SEARs).
Early 2027
DPHI issues the SEARs for the project with input from other government agencies, identifying information required in the EIS.
Early 2027 – late 2028
Origin undertakes comprehensive investigations into the environmental and social impacts of the project as part of the project.
Late 2028
The EIS is exhibited for at least 28 days, inviting submissions from community and stakeholders.
Mid 2029
Origin publishes a report, responding to submissions received and sharing any changes to our proposal.
Late 2029
DPHI considers the EIS and RTS report to determine the merit of the proposal.
2030
DPHI makes a determination on the project and issues consent conditions if approved
2031 onwards
Origin begins approved demolition and rehabilitation works
Project Fact Sheets
Project summary >
Our engagement approach >
The SSD process provides a formal opportunity for feedback on the project during the exhibition of the Environment Impact Statement; however, we invite feedback from the community throughout this process.
Further information on the Eraring Site Decommissioning Project and key planning documents are available on the NSW Planning Portal.
Keep in touch
Keeping our community and stakeholders informed as our proposal develops is a priority. We will update this site as new information becomes available.
For direct project updates, subscribe to our e-news using the form at the end of the page.
Contact our team
E: eraring@originenergy.com.au
P: 1800 677 315
Frequently asked questions
When will the Eraring Power Station close?
Origin advised the Australian Energy Market Operator (AEMO) that it will extend the operation of all four units of the Eraring Power Station to 30 April 2029, to support energy supply in NSW through the energy transition.
What does the decommissioning of the Eraring site involve following the retirement of the power station?
Origin is planning for the decommissioning of the Eraring site to a condition that will enable us to consider options for future uses of the site. This will involve the demolition of the power station and supporting infrastructure followed by rehabilitation of the site.

What does retirement involve?
The retirement of Eraring Power Station will include both the end of energy generation at the Eraring site and the subsequent process required to make the operating facility safe after operations have ceased. This involves removing hazards and sources of energy and transitioning the plant into a state ready for its eventual demolition and rehabilitation.
Retirement forms a part of Eraring’s existing approvals as it will not involve an intensification of activity on the site or new development and will be managed in consultation with regulatory authorities.
What does decommissioning involve?
Decommissioning is the process Origin will undertake to complete the demolition and rehabilitation of the broader Eraring Site to a condition that is safe and stable following the retirement of the power station.
We are undertaking studies to refine our approach but expect that the key activities to be undertaken during these stages will include:
- Demolition and rehabilitation of the infrastructure on the Eraring site including cooling water infrastructure.
- Capping and rehabilitation options or transition of the Eraring Ash Dam (ERAD) for resource recovery purposes prior to installation of a cap and rehabilitation.
- Offsite hazardous materials disposal or construction and use of a hazardous materials disposal facility
Once the redundant infrastructure is demolished, rehabilitation works will continue at the site for a number of years.
Demolition of the infrastructure of the Eraring Power Station will only commence after government approvals have been attained.
What approvals are required to begin decommissioning of the site?
We are currently seeking approvals for the decommissioning of the power station site, which will occur following the retirement of coal fired power generation at Eraring.
Approval for the decommissioning of the Eraring site will need to be obtained through the NSW State Significant Development (SSD) Process. While obtaining these approvals is a critical step for the Eraring site following the retirement of the Eraring Power Station, the approval will not influence the retirement date. The approval process is separate to planning for the closure and retirement of the Eraring Power Station.
The SSD process is a lengthy regulatory process that involves consultation with the community and stakeholders and investigations to assess the potential social and environmental impacts of the decommissioning works. The findings of this work are collated into an EIS that is publicly displayed and assessed by the Minister for Planning.
Origin will also seek approval from the federal government, in accordance with the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act). This process will run alongside the SSD process and determination of our application is expected to be made on assessment of the EIS.
When is the decommissioning of the site planned to happen?
Securing approvals is a complex and lengthy undertaking that reflects the complex nature of the demolition and rehabilitation works.
We anticipate the approval process will take approximately 5 years and are beginning the process now to minimise the delay between ceasing coal fired power generation at Eraring and obtaining these approvals.
The decommissioning of the Eraring site will also take a number of years once approvals have been gained.
What environmental impacts will the decommissioning works have?
We are currently in an early phase of the SSD process undertaking long lead environmental and engineering studies to refine our decommissioning methodology and understand the potential environmental and social impacts of each approach.
We have engaged a leading provider of demolition services with experience in power station demolition to assist us in early planned work for the station’s eventual demolition.
As we progress further through the approval process and develop an EIS, Origin will complete comprehensive assessments of the proposed demolition and rehabilitation methodologies.
Where possible, we will aim to reuse and recycle components of the power station.
What is Origin planning to do with the Eraring Ash Dam?
A major by-product of coal generation is coal ash. Some of the coal ash produced at Eraring Power Station is recovered for recycling and used as a construction material or to produce concrete. Excess ash is stored in the Eraring Ash Dam.
Our preferred option following closure is to pursue resource recovery and recycling opportunities for the ash deposits in the Ash Dam.
If we pursue this option, it is expected that ash deposits not suitable for resource recovery will be capped once recovery work has been completed.
In parallel, a more traditional cap and close scenario is also being developed as an alternate option for the closure of the Ash Dam.
Our approach to managing the Ash Dam will continue to develop and be informed by ongoing studies and resource recovery market conditions.
What is Origin planning to do with the Eraring site after decommissioning?
The installation of the Eraring Battery is the biggest step that Origin is currently taking toward the future use of the Eraring Site beyond the retirement of EPS.
The first Eraring Battery commenced commercial operation in January 2026 marking the first step in the transition of the Eraring site for future use. Eraring Battery 2 is expected to come online in early 2027, together delivering a total of 700MW / 3,160MWh that will provide an average of 4.5 hours of storage capacity in NSW.
A new battery development is now in planning, which would add a 500MW, 10-hour battery, co-located with the existing development.
Origin will consider opportunities as they develop and has identified energy, industry, and technology as the most likely future uses.
The Eraring Site Decommissioning Project and return of the site to a safe and stable state is a vital step towards enabling options for potential repurposing or future use of the site, but does not include the planning, approvals or consultation for the future use of the site.
Any potential development and re-purposing activities at the Eraring site, including any additional rehabilitation of the site to support those activities, will require separate approvals.
How are the staff at the power station being supported through the site transition?
We have established the Future Directions program to support our people through Eraring’s future retirement and to contribute to the safe and reliable operations at the plant in its final years.
The dedicated Future Directions team provides ongoing, individualised career planning, training, consultation, communication and wellbeing transition support to Eraring employees and leaders.