Origin Energy’s 1.5GW Yanco Delta Wind Farm development project in southern New South Wales (NSW) has secured a full, 1,460 MW allocation of transmission access rights from EnergyCo, representing another major milestone in the potential development of this large-scale renewable energy project.

Located on a 33,000-hectare site 10 kms north-west of Jerilderie in the NSW Government-designated South West Renewable Energy Zone (REZ), Yanco Delta Wind Farm is a large and advanced wind project.

With transmission access rights secured, Origin will continue to progress a range of other development activities that will support a Final Investment Decision (FID) on Yanco Delta, targeted for the middle of the 2027 financial year. These activities include further project design works, amendments to planning approvals, referral of environmental approvals, undertaking generator performance standard assessments with Transgrid and AEMO, and finalising appointment of construction partners and a turbine supplier. Origin is also focussed on implementing a comprehensive program to share benefits of the development with the community.

Origin CEO Frank Calabria said, “Securing transmission access rights is another important milestone for the Yanco Delta Wind Farm development project and recognises the important role it can play in delivering renewable energy supply to help meet the demand of households and businesses in NSW.

“This represents another major step in Origin’s commitment to add 4-5 GW of renewables and storage to our portfolio, alongside around $1.7 billion being invested in large scale battery storage projects currently under construction.

“As a result, Origin is well on the way to transitioning our portfolio towards cleaner forms of energy supply, firmed by batteries, pumped hydro and the nation’s leading gas peaking fleet to underpin reliable supply to customers under all scenarios.

“We look forward to continuing to work closely with our host landowners and local stakeholders to develop and construct Yanco Delta Wind Farm in a way that minimises impacts and ensures the region gets to share in the benefits that will flow from a project of this scale,” Mr Calabria said.

Origin continues to assess a range of capital efficient options to finance construction of Yanco Delta Wind Farm development project, including through partnerships with capital providers. Origin intends to contract for all, or the majority, of the offtake from the wind farm.

Origin completed the acquisition of the Yanco Delta Wind Farm from Virya Energy in May 2024. The consideration consisted of an upfront payment of $125 million to Virya Energy, with the securing of access rights triggering a final milestone payment of $175 million.

In addition to Yanco Delta, Origin’s portfolio of wind farm developments includes the proposed Skye Ridge and Northern Tablelands Wind Farms in the New England REZ with a planned capacity of more than 1,350 MW.  Progress also continues on Origin’s large-scale batteries under construction at Eraring and Mortlake power stations.