Origin Energy Limited (Origin) has released its Quarterly Report for the period to 31 March 2024 covering the performance of its Integrated Gas, Energy Markets and Octopus Energy segments. 

Integrated Gas:

  • Australia Pacific LNG revenue for the March quarter was 7 per cent higher than the prior quarter, at $2,553 million with both higher volumes and prices. Revenue for FY2024 to date was 16 per cent lower than the corresponding FY2023 period, primarily due to lower realised oil prices and lower short-term domestic contract prices.
  • March quarter production was 5 per cent higher than the prior quarter, which was impacted by the unplanned turndown in production related to an LNG vessel that lost power at the Curtis Island facility in November 2023.
  • Production for FY2024 to date was 4 per cent higher compared with the same period in FY2023, driven by increased wells online and effective well and field optimisation activity, partially offset by the unplanned production turndown last November.
  • The March quarter Australia Pacific LNG realised average LNG price was US$12.17/mmbtu (contracted and spot) and the average domestic price was A$6.90/GJ (legacy and short-term).

Energy Markets:

  • Retail electricity sales volumes were steady compared with the March 2023 quarter, with increased demand from warmer weather and higher customer numbers offset by lower household usage due to solar uptake and energy efficiency.
  • Gas sales volumes declined 14 per cent compared with the March 2023 quarter, as warmer weather contributed to a reduction in retail volumes and business volumes also declined, reflecting lower short term trading sales and net customer losses. Gas used for power generation rose 34 per cent compared with the March 2023 quarter to support increased electricity demand due to warmer weather.
  • Acquired renewable energy developer Walcha Energy1 and in April Origin signed an agreement to acquire 1.5 GW wind farm project Yanco Delta2.
  • Signed an offtake agreement for the first stage of 260 MW two-hour Supernode battery in Queensland, with full orchestration rights. The battery is expected to be operational in the second half of 2026.
  • Signed an agreement with Superloop3 for the provision of broadband wholesale services, also acquiring an equity interest in Superloop.
  • We remain in discussion with the NSW Government on the closure date for the Eraring Power Station.

Octopus Energy:

  • Origin’s additional £280 million (~$530 million) investment in Octopus Energy, announced in December completed on 11 April 2024, with Origin’s interest increased to ~23 per cent.
  • Octopus continued its strong organic customer growth in the quarter, adding over 400,000 customer accounts in the UK and international retail businesses.
  • Completed migration of all 1.3 million Shell customers in two months, beating Octopus’ previous industry record by four months.

Origin CEO Frank Calabria said, “Australia Pacific LNG is performing well operationally, continues to be a major supplier to the domestic market, and recently marked the milestone of its one thousandth LNG cargo. Australia Pacific LNG is a world class operation by any measure, and this is a remarkable achievement that is testament to the hard work of so many.

“In Energy Markets, we continue to make significant progress in executing our strategy to grow renewable energy and storage in the portfolio.

“Origin recently signed an agreement to acquireYanco Delta, one of the largest and most advanced wind and storage projects in New South Wales, and also purchased renewable energy developer Walcha Energy, including its proposed Ruby Hills Wind Farm and Salisbury Solar Farm projects in the New South Wales renewable energy zone.

“We continue to progress large-scale batteries under development at Eraring and Mortlake power stations, and recently announced our first storage offtake agreement from the Supernode battery in Queensland, taking Origin’s storage portfolio to around 1 GW of capacity once these batteries come online,” Mr Calabria said.

 UnitMar-24 QTR Dec-23 QTR % Change Mar-23 QTR % ChangeFYTD-24FYTD-23% Change 
Integrated Gas – APLNG 100%
ProductionPJ176.2167.45%165.07%518.5498.04% 
SalesPJ167.6160.44%158.26%488.4480.42% 
Commodity revenue$m2,5532,3807%2,764(8%)7,2798,716(16%) 
Average realised LNG priceUS$/mmbtu12.1711.883%14.50(15%)11.9014.87(20%) 
Average realised Domestic gas price$/GJ6.906.398%6.1712%7.199.11(21%) 
Energy Markets         
Electricity salesTWh8.99.0(0%)9.1(2%)27.027.2(1%) 
Natural gas salesPJ35.546.2(23%)38.1(7%)140.7161.8(13%) 
Consolidated Origin 
Capex$m19315624%72168%49534145% 
Investments$m1784(79%)20(13%)169192(12%) 

1 Refer to the media release for more details: https://www.originenergy.com.au/about/investors-media/origin-acquires-renewables-developer-walcha-energy/

2 Refer to the ASX release for more details: https://announcements.asx.com.au/asxpdf/20240412/pdf/062fnpmgh9v5n8.pdf

3 Refer to the media release for more details: https://www.originenergy.com.au/about/investors-media/origin-and-superloop-sign-broadband-services-agreement/